Skip to main content

Traffic Advisory: Portions of Campus Drive to Close

Construction will take place July 15 to Aug. 9

Beginning July 15, portions of Campus Drive will be closed over several weeks to "through traffic" as part of an ongoing construction project to install piping from West Campus to assist in the cooling of buildings on East Campus.

The closures are taking place so crews will have full access to Campus Drive for 24-hour construction. The work includes tearing up the road and laying pipe. Crews will be on-hand to help direct "local" traffic for residents who must travel along Campus Drive.

Here is the breakdown of when and where construction will take place, which runs from July 15 to Aug. 9:

July 15 to July 28Road closed between Swift and Alexander avenues.Duke transit impact: No bus stop outside Nasher Museum of Art.

July 22 to Aug. 4Road closed between Chapel Drive roundabout and Anderson Street.Duke transit impact: No bus stop outside Nasher Museum of Art or Undergraduate Admissions.

July 29 to Aug. 9Road closed between Swift Avenue and 147 bridges on Campus Drive.Duke transit impact: No bus stop outside Nasher Museum of Art or at bottom of Gattis Street extension at Arts Annex stop.

Aug. 4 to Aug. 9Road closed between Anderson Street and Alexander Drive.Duke transit impact: None.

Duke community members with questions about Duke bus services during construction periods can call (919) 684-2218 for more information.

During construction, sidewalks will remain open for pedestrian traffic, except between Swift Avenue and the 147 bridges, which has been closed since May as part of the pipe installation project.